Aphrodite Development
FEED & Path to FID

Aphrodite is one of Cyprus's two lead gas projects. Its development plan was approved in February 2025, FEED began in December 2025, and in April 2026 the partners initialed a 15-year term sheet with Egypt's EGAS for the field's entire output. FID has not yet been taken — it is targeted for late 2026 to 2027, with first gas around 2030-31.

Most Advanced Project
~2.9 Tcf
Sanctioned 2C
NSAI, Feb 2026
1,700m
Water Depth
Block 12
5,500m
Reservoir Depth
Below sea level
~$4B
Development CAPEX
Approved plan

Updated October 2026 · Sources: NSAI, Feb 2026 (sanctioned phase)primary, MECI, NewMed Energy

Development Progress

Overall Progress to First Gas 60%
Discovery & Appraisal
2011-2014
Complete
Concept Selection
2015-2024
Complete
Development Plan Approval
Feb 2025
Complete
FEED Engineering
Dec 2025-
In Progress
Egypt Gas Sales Terms
Apr-May 2026
In Progress
FID
Late 2026-2027
Pending
Construction
2027-2030
Pending
First Gas
~2030-31
Pending

Updated October 2026 · Sources: MECI, NewMed Energy, company disclosures

Current Phase: FEED & Path to FID

With the development plan approved and key Egyptian offtake terms initialed, the project is in front-end engineering ahead of a final investment decision targeted for late 2026 to 2027:

1. Development & Production Plan

Approved Feb 2025

Cyprus approved the updated plan and amended the production sharing contract on 14 February 2025: a floating production unit in the Cyprus EEZ, four initial production wells, an export pipeline to Egypt and a nominal capacity of around 800 MMcf/d, at an estimated total field cost of roughly $4 billion. NSAI's resource update (effective 28 February 2026) certifies 2C contingent resources of 2,881 Bcf (~2.9 Tcf) for the sanctioned phase, plus ~784 Bcf classed as development unclarified (~3.7 Tcf total) and 6.3 MMbbl of condensate.

2. Egypt Gas Sales Terms

Term Sheet Apr 2026

In April 2026 the partners initialed (not yet finalized) a 15-year term sheet with EGAS covering the field's entire output — around 700 MMcf/d (~7.2 bcm/yr), Brent-linked — delivered via a new ~$2 billion subsea pipeline to Port Said, feeding the Egyptian grid and LNG plants with potential re-export to Europe. A Host Government Agreement for the transmission project was agreed alongside, and on 19 May 2026 the Cyprus cabinet approved the basic Gas Sales Agreement terms. Final GSAs are still to be signed.

3. FEED & Final Investment Decision

In Progress

Partners approved FEED on 23 December 2025 (~$105.7 million of a $111.5 million 2026 budget). FID has not been taken: Egypt is pushing for September 2026, while Cyprus Energy Minister Michael Damianos (30 June 2026) targets December 2026 to January 2027. NewMed conditions FID on FEED results, pipeline commercial arrangements and final gas sales agreements. Pipeline construction is planned from 2027, with first gas to Port Said around 2030-31.

Technical Readiness

Completed

  • ✓ 3D seismic acquisition & interpretation
  • ✓ Discovery & appraisal wells (2 wells)
  • ✓ Reservoir modeling & NSAI resource certification (Feb 2026)
  • ✓ Development plan government approval (Feb 2025)
  • ✓ EGAS term sheet initialed; GSA terms cabinet-approved (Apr-May 2026)

Pending FID

  • ○ FEED completion (underway since Dec 2025)
  • ○ Final gas sales agreements & pipeline commercial arrangements
  • ○ Final Ishai (Israel) unitization deal — in-principle agreement Jan 2026
  • ○ EPC contract awards (subsea, pipeline)
  • ○ Long-lead equipment ordering
  • ○ Construction vessel booking
  • ○ Production license issuance

Risk Factors

Commercial Risks

Monitored
  • • Egypt capacity constraints/availability
  • • LNG price volatility affecting GSA terms
  • • Partner alignment on investment
  • • Financing market conditions

External Risks

Monitored
  • • Geopolitical tensions in region
  • • Regulatory/permitting delays
  • • Supply chain constraints
  • • Turkey maritime disputes
Outlook

Next Steps to First Gas

2026
Complete FEED, sign final gas sales agreements, close pipeline commercial arrangements and financing
Late 2026-2027
FID — Final Investment Decision (Egypt pushes for Sep 2026; Cyprus targets Dec 2026-Jan 2027)
2027-2030
Construction phase (subsea, pipeline to Port Said, facilities)
~2030-31
First Gas Production
Full Timeline to First Gas

Aphrodite in the News

Rigzone • Oct 27

Egypt Agrees Tax Relief for Project to Import Cyprus Gas

The Chevron-led Aphrodite consortium and the Egyptian government have agreed on a special tax regime for a project that would enable the piped export of 100 percent of production from the field offshore Cyprus to the North African country.

Offshore Engineer • Oct 21

Chevron, Egypt Ink Fiscal Agreement for Aphrodite Gas Project

Egypt and Chevron have signed an agreement establishing the fiscal framework for developing and connecting Cyprus’ offshore Aphrodite gas to Egyptian gas infrastructure…

Cyprus Mail • Oct 19

Aphrodite development might be best left on hold, warns analyst

Cyprus may be left with negligible profits from future gas sales from the Aphrodite reservoir if it agrees to Chevron’s latest demands, an energy analyst warned on Monday. Charles Ellinas was referring to Chevron – operator of the Aphrodite field – recently asking Cyprus to pay a tariff of $3 per...

Offshore Technology • Aug 3

Shell to sell BG Cyprus and Aphrodite gas stake to MOL Group

Shell has agreed to sell its wholly-owned subsidiary BG Cyprus and its Aphrodite gas field stake to MOL Group for up to $720m.

Splash247 • Aug 3

MOL buys Shell stake in Cyprus gas field for $720m

Hungary’s MOL has signed an agreement to acquire BG Cyprus, a 100% subsidiary of supermajor Shell, which holds a 35% non-operated interest in the Aphrodite gas field in the eastern Mediterranean. This acquisition is the biggest E&P growth opportunity for the company since acquiring a 9.57% stake ...